LRSP2-ESS Implementation

Environmental and Social Safeguard Monitoring Report
Timeline : 16/03/2023 -
Sponsor by : World Bank
LRS2_E&S Safeguard Monitoring Report_July 2022-Jun2023_Vol 1 Main Report
Timeline : 01/07/2022 - 30/06/2023
Sponsor by : World Bank

ໂຄງການສ້າງແຜນຈັດຕັ້ງປະຕິບັດຕົວເມືອງສີຂຽວ ສຳລັບນະຄອນຫຼວງວຽງຈັນ

NR13S(12 bridges Construction)

TERMS OF REFERENCE
Timeline : 14/08/2024 -
Sponsor by : EIB

NR13S(Supervision Consultant)

SWSSHP

ທະນາຄານໂລກ

ືNR13S EIB 8 Bridges Construction

Hydrology Report Package 2 (06.10.2023)
Timeline : 13/06/2024 -
Sponsor by : EIB
Hydrology Report Package 4 (Update 6.10.2023)
Timeline : 13/06/2024 -
Sponsor by : EIB
FINAL DESIGN REPORT_14 BRIDGES_NR13S
Timeline : 13/06/2024 -
Sponsor by : EIB